Generators G1 100 MVA 138 kV G2 200 MVA 150 kV Transformers
Generators
G1: 100 MVA, 13.8 kV
G2: 200 MVA, 15.0 kV
Transformers
T1: 100 MVA, 13.8 kV/230 kV, XT1=0.1 pu
T2: 200 MVA, 15.0 kV/230 kV, XT2=0.1 pu
Transmission Lines
All lines 230 kV, z = 0.08+j0.5 ohm/km
Line lengths are
Line-1=15 km,
Line-2=50 km,
Line-3=40 km,
Line-4=15 km,
Line-5=50 km
System Base Quantities
Sbase = 100 MVA (Three-phase)
Vbase = 13.8 Kv (Line-to-line) in the zone of G1
Generator, line, transformer data information and one-line diagram of 7 bus system are given above. Besides, all transformers have same turn ratio which is 1. Using the given system, solve the system for power flow analysis with Newton Raphson Method. In this homework, MATPOWER simulation package will be used to solve power flow problem for the given system.
I NEED VERY DETAILED ANSWER FOR MY HOMEWORK.THANX
G1 G2 180 MW V11-13.8kV BUS 1 BUS 7 IV71-15.0kV T1 T2 BUS 2 Line-5 BUS 5 30 MVAr 30 MVAr 50 M 50 MW Line-1 Line-4 BUS 3 BUS 4 Line-2 Line-3 30 MVAr 50 MW 30 MVAr 50 MW 30 MVAr 50 MW BUS6 The on-line diagram of 7 bus systemSolution
Case file is as follows;
function mpc = case7
 %% MATPOWER Case Format : Version 2
 mpc.version = \'2\';
%%----- Power Flow Data -----%%
 %% system MVA base
 mpc.baseMVA = 100;
%% bus data
 %   bus_i   type   Pd   Qd   Gs   Bs   area   Vm   Va   baseKV   zone   Vmax   Vmin
 mpc.bus = [
    1   3   0   0   0   0   1   1   0   13.8   1   1.1   0.9;
    2   1   50   30   0   0   1   1   0   230   1   1.1   0.9;
    3   1   50   30   0   0   1   1   0   230   1   1.1   0.9;
    4   1   50   30   0   0   1   1   0   230   1   1.1   0.9;
    5   1   50   30   0   0   1   1   0   230   1   1.1   0.9;
    6   1   50   30   0   0   1   1   0   230   1   1.1   0.9;
    7   2   0   0   0   0   1   1   0   15   1   1.1   0.9;
 ];
%% generator data
 %   bus   Pg   Qg   Qmax   Qmin   Vg   mBase   status   Pmax   Pmin   Pc1   Pc2   Qc1min   Qc1max   Qc2min   Qc2max   ramp_agc   ramp_10   ramp_30   ramp_q   apf
 mpc.gen = [
    1   0   0   300   -300   1   100   1   250   10   0   0   0   0   0   0   0   0   0   0   0;
    2   180   0   300   -300   1   100   1   300   10   0   0   0   0   0   0   0   0   0   0   0;
 ];
%% branch data
 %   fbus   tbus   r   x   b   rateA   rateB   rateC   ratio   angle   status   angmin   angmax
 mpc.branch = [
    1   2   0   0.1   0   100/3   100/3   100/3   0   0   1   -360   360; %pu converted to actual impedance
    4   5   12   7.5   0   250   250   250   0   0   1   -360   360;
    5   6   40   25   0   250   250   250   0   0   1   -360   360;
    3   6   40   25   0   300   300   300   0   0   1   -360   360;
    5   7   0   0.05   0   200/3   200/3   200/3   0   0   1   -360   360; %pu converted to actual impedance
    6   4   32   20   0   250   250   250   0   0   1   -360   360;
    2   3   12   7.5   0   250   250   250   0   0   1   -360   360;
 ];
%%----- OPF Data -----%%
 %% generator cost data
 %   1   startup   shutdown   n   x1   y1   ...   xn   yn
 %   2   startup   shutdown   n   c(n-1)   ...   c0
 mpc.gencost = [
    2   1500   0   3   0.11   5   150;
    2   2000   0   3   0.085   1.2   600;
 ];
Bus type (1 = PQ, 2 = PV, 3 = ref, 4 = isolated)
RateA is MVA rating phase A line
Add folder matpower and and t inside matpower.
Check matpower with code,
test_matpower;
Result;
 t_nested_struct_copy....ok
 t_mpoption..............ok
 t_loadcase..............ok
 t_ext2int2ext...........ok
 t_jacobian..............ok
 t_hessian...............ok
 t_margcost..............ok
 t_totcost...............ok
 t_modcost...............ok
 t_hasPQcap..............ok
 t_mplinsolve............ok (2 of 4 skipped)
 t_mips..................ok
 t_qps_matpower..........ok (252 of 360 skipped)
 t_miqps_matpower........ok (226 of 240 skipped)
 t_pf....................ok
 t_cpf...................ok
 t_islands...............ok
 t_opf_model.............ok
 t_opf_fmincon...........ok
 t_opf_mips..............ok (101 of 202 skipped)
 t_opf_mips_sc...........ok (101 of 202 skipped)
 t_opf_dc_mips...........ok
 t_opf_dc_mips_sc........ok
 t_opf_dc_ot.............ok (4 of 92 skipped)
 t_opf_userfcns..........ok
 t_opf_softlims..........ok
 t_runopf_w_res..........ok
 t_dcline................ok
 t_get_losses............ok
 t_makePTDF..............ok
 t_makeLODF..............ok
 t_printpf...............ok
 t_total_load............ok
 t_scale_load............ok
 t_psse..................ok
 All tests successful (3014 passed, 686 skipped of 3700)
 Elapsed time 58.64 seconds.
Now type following codes;
mpc = loadcase(case7);
 runpf(case7);
result;
MATPOWER Version 5.1, 20-Mar-2015 -- AC Power Flow (Newton)
Newton\'s method power flow did not converge in 10 iterations.
>>>>> Did NOT converge (0.03 seconds) <<<<<



