17 For which costs is a volume variance computed A Fixed man
17. For which cost(s) is a volume variance computed? A. Fixed manufacturing overhead only B. Direct labor costs as well as overhead costs C. Variable manufacturing overhead only D. Both variable and fixed manufacturing overhead
Solution
Option A ) Fixed manufacturing overhead only
formula:Budgeted fixed overhead -Fixed overhead applied to work in process.