If the daily demand is 50 and the lead time in days is 4 wha
If the daily demand is 50 and the lead time in days is 4, what is the reorder point?
Solution
If the daily demand is 50 and the lead time in days is 4, what is the reorder point?
Ans.:
Reorder point = daily demand x lead time + safety stock
= 50 X 4+0=200