7 To prevent future issues with items not shown as they were
7. To prevent future issues with items not shown as they were actually constructed, it is a good idea to collect _____ and using them to have final set of plans drawn up by the architect.
a. a last set of construction plans
b. the first set of construction plans without revisions
c. a last set of construction plans showing all previous recvisions and red-line drawings
d. a list of plan modifications obtained from building inspection personnel
Solution
To prevent future issues with items not shown as they were actually constructed, it is a good idea to collect _____ and using them to have final set of plans drawn up by the architect.
Answer
C. a last set of construction plans showing all previous revisions and red line drawings