7 To prevent future issues with items not shown as they were

7. To prevent future issues with items not shown as they were actually constructed, it is a good idea to collect _____ and using them to have final set of plans drawn up by the architect.

a. a last set of construction plans

b. the first set of construction plans without revisions

c. a last set of construction plans showing all previous recvisions and red-line drawings

d. a list of plan modifications obtained from building inspection personnel

Solution

To prevent future issues with items not shown as they were actually constructed, it is a good idea to collect _____ and using them to have final set of plans drawn up by the architect.

Answer

C. a last set of construction plans showing all previous revisions and red line drawings

7. To prevent future issues with items not shown as they were actually constructed, it is a good idea to collect _____ and using them to have final set of plans