Solution
Part a)
Predetermined Overhead Rate = Estimated Manufacturing Overhead Cost / Estimated Direct Labor Hours
 Estimated Manufacturing Overhead Cost = $180,000 + ($1.00 * 60,000)
 Estimated Manufacturing Overhead Cost = $180,000 + $60,000
 Estimated Manufacturing Overhead Cost = $240,000
Predetermined Overhead Rate = 240,000 / 60,000
 Predetermined Overhead Rate = $4.00 per DLH
Part b)
Total Manufacturing Cost of Job 550 = Direct Materials + Direct Labor + Manufacturing Overhead applied
 Manufacturing Overhead applied = $4.00 * 15 = $60
 Total Manufacturing Cost of Job 550 = $213 + $323 + $60
 Total Manufacturing Cost of Job 550 = $596
Part c)
Selling Price = Manufacturing Cost + Markup
 Selling Price = $596 + ($596 * 200%)
 Selling Price = $596 + $1,192
 Selling Price = $1,788
Answer to Requirement 2.
Part a)
Predetermined Overhead Rate = Estimated Manufacturing Overhead Cost / Estimated MachineHours
 Estimated Manufacturing Overhead Cost = $180,000 + ($2.00 *30,000)
 Estimated Manufacturing Overhead Cost = $180,000 + $60,000
 Estimated Manufacturing Overhead Cost = $240,000
Predetermined Overhead Rate = 240,000 /30,000
 Predetermined Overhead Rate = $8.00 per MH
Part b)
Total Manufacturing Cost of Job 550 = Direct Materials + Direct Labor + Manufacturing Overhead applied
 Manufacturing Overhead applied = $8.00 * 5 = $40
 Total Manufacturing Cost of Job 550 = $213 + $323 + $40
 Total Manufacturing Cost of Job 550 = $576
Part c)
Selling Price = Manufacturing Cost + Markup
 Selling Price = $576 + ($576 * 200%)
 Selling Price = $576 + $1,152
 Selling Price = $1,728