Calculate the IRR for each project Do not round intermediate
Calculate the IRR for each project. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)
What is the crossover rate for these two projects? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
| Consider the following two mutually exclusive projects: |
Solution
Year
Project X cash flow
0
-20900
1
9075
2
9550
3
9025
IRR =Using IRR function in MS excel =irr(-20900,9075,9550,9025)
15.42%
Year
Project Y cash flow
0
-20900
1
10550
2
8025
3
8925
IRR =Using IRR function in MS excel =irr(-20900,10550,8025,8925)
15.63%
Year
Project X cash flow
Project Y cash flow
Differential cash flow
0
-20900
-20900
0
1
9075
10550
1475
2
9550
8025
-1525
3
9025
8925
-100
Cross over rate =Using IRR function in MS excel =irr(0,1475,-1525,-100)
9.58%
| Year | Project X cash flow | ||
| 0 | -20900 | ||
| 1 | 9075 | ||
| 2 | 9550 | ||
| 3 | 9025 | ||
| IRR =Using IRR function in MS excel =irr(-20900,9075,9550,9025) | 15.42% | ||
| Year | Project Y cash flow | ||
| 0 | -20900 | ||
| 1 | 10550 | ||
| 2 | 8025 | ||
| 3 | 8925 | ||
| IRR =Using IRR function in MS excel =irr(-20900,10550,8025,8925) | 15.63% | ||
| Year | Project X cash flow | Project Y cash flow | Differential cash flow |
| 0 | -20900 | -20900 | 0 |
| 1 | 9075 | 10550 | 1475 |
| 2 | 9550 | 8025 | -1525 |
| 3 | 9025 | 8925 | -100 |
| Cross over rate =Using IRR function in MS excel =irr(0,1475,-1525,-100) | 9.58% |