39 A batch production plant works 40 hours per week and has
Solution
R p =1 / t b
R p = Average production Rate (parts/ min)
T b = Average production time (parts /min)
Machine 1
R p1 =1 / t b1
Part A
10= 1/15
=0.66
Part B
15=1/14
=1.07
Part D
20=1/5
=4
Machine 2
R p2 =1 / t b2
Part A
15=1/10
=1.5
Part c
8=1 / 21
=0.38
Part d
25= 1/4
=6.25
Part E
16= 1/ 5
=3.2
Machine 3
R p3 =1 / t b3
Part A
18.75 = 1/8
=2.34
Part B
10=1/21
=0.48
Part E
10= 1/8
=1.25
____________________________________________________________________________________
b) No only Machine 2 working for 40 hours
b) Machine 2 working capacity of 40 hours, machine 1 having 34 hours ,Machine 3 having 37 hours
For Machine 1
Added Part c for 6 hours (Already 34 hours +6 hours = 40 hours
For Machine 3
Added Part d for 3 hours( Already 37 hours +3 hours =40 hours)
_____________________________________________________________________________________