With iterative techniques project progress can be measured m

With iterative techniques, project progress can be measured most effectively by: a. counting the number of team meetings held in a 4-8 week time frame b. counting lines of code that have been written c. looking at product backlog d. counting the number of interactions between team members and the customer

Solution

Answer:

D.counting the number of interactions between team members and the customer

With iterative techniques, project progress can be measured most effectively by: a. counting the number of team meetings held in a 4-8 week time frame b. counti