Use RS Means 2Calculate the duration and labor hours to inst
Use RS Means.
2.Calculate the duration and labor hours to install a gymnasium flooring that is 3,450 sf.Floor is to be maple flooring over sleepers, #2 & better, 33/32” thick
Solution
SOLUTION
FLOOR AREA : 3450 Sft
For 1 Hour Labour Productivity - 19 Sft Per Hour
So Total Labour Hours = (3450/19) = 181.58 hrs
Total Duration = 181.58 hrs / (8 hours per day) = 22.7 days