You are the project manager of a new office building and you
You are the project manager of a new office building, and your field superintendent has informed you that the numerous dimensioning problems have resulted in an inefficient operation. What rights and obligations does A201 give you to resolve this problem?
Solution
According to clause 13.5.3 of A201-1997,
Rights and Obligations to resolve Problem - when a portion of work does not meet requirements as per contractor documents,
All costs made necessary by such failure including those of repeated procedures and compensation for the Architect\'s services and expenses shall be at the Contractor\'s expense
the improvement in work done by the contractor under the guidance of Architect, All delays and loss in work should be expensed by the contractor.