Which project delivery method would be most appropriate for
Which project delivery method would be most appropriate for the following scenario?
Dignity Health is planning to build a new hospital in Northern California. This state-of-the-art hospital will take approximately 5 years to plan, design, and construction. Dignity Health would like to use a delivery method that identifies the project team at the very beginning and shares the risk across all key team members.
Design/Build
Integrated Project Delivery
CM Multiple Prime
CM at Risk
Design-Bid-Build
| Design/Build | ||
| Integrated Project Delivery | ||
| CM Multiple Prime | ||
| CM at Risk | ||
| Design-Bid-Build |
Solution
As per the given requirements above for the better construction and procedure \"Integrated Project Delivery\" can be used it is so because of the following
IPD leverages early contributions of knowledge and expertise through utilization of new technologies, allowing all team members to better realize their highest potentials while expanding the value they provide throughout the project lifecycle. At the core of an integrated project are collaborative, integrated and productive teams composed of key project participants. Building upon early contributions of individual expertise, these teams are guided by principles of trust, transparent processes, effective collaboration, open information sharing, team success tied to project success, shared risk and reward, value-based decision making, and utilization of full technological capabilities and support. The outcome is the opportunity to design, build, and operate as efficiently as possible.
Simply we can say this is what the INTEGRATED PROJECT DELIVERY comprises off and it is the best delivery method for to build a new hospital in Northern California by Dignity Health