Question 2 Under Conclusion write if you think based on your

Question #2 Under \"Conclusion?\" write if you think (based on your data} whether this project is ahead of schedule or behind schedule. Also, if is over budget or under budget.

EVM Exercise – MGT 751 – Week 7

Worksheet 1 (Question #1)

Activity

Budget

PV

EV

AC

SV

CV

Task 1

8

10

Task 2

10

12

Task 3

4

3

Task 4

12

12

Task 5

6

8

Task 6

18

0

Task 7

6

6

Task 8

12

2

Task 9

10

0

Task 10

6

3

Task 11

8

0

Task 12

10

0

Task 13

12

12

Task 14

12

0

Task 15

8

0

BAC

142

68

EVM Exercise – MGT 751 – Week 7

Worksheet 2

SHOW YOUR WORK (Question #2)

SPI =

CPI =

EAC =

ETC =

VAC =

Conclusions?

EVM Exercise - MGT 751 - Week 7
This is the Gantt Chart you will use in this exercise to determine the state of this project using various
EVM formulas.
Period Poriod Period Poriod Period Poriod Pcriod Period |Period Potiod Artivity Rludget Activity Ridget1 Tack 2 10 Task 4 Task 12 Tack 5 Task A Task 7 Tack 8 12 lask 11 6 6 Task 10 6 Tak 8 lask 121U Task 13 2 l ime Task 1312 Task 14 12 lask 1 LI BAC 112

Solution

Calcuations:

Planned value for

Task 1 = 6+2 = 8

Task 2 = 2+7+1 =10

Task 3 = 4

Task 4 = 3+6+3 = 12

Task 5 = 4+2 = 6

Task 6 =4+4+4+4 = 16

Task 7 = 4+2 =6

Task 8 =4+4+4 = 12

Task 9 =5+5 =10

Task 10 =3+3 =6

Task 11 =2+4+2 = 8

Task 12 = 4+8 =12

Task 13 = 6+6 =12

Task 14 =2+6+6 = 14

Task 15 =1+7 = 8

Calculation of EV :

100 % completion

Task 1 = 6+2 = 8

Task 2 = 2+7+1 =10

Task 3 = 4

Task 4 = 3+6+3 = 12

Task 5 = 4+2 = 6

Task 6 =4+4+4+4 = 16

50% completion

Task 7 = 4+2 =6 = 3

0 % completion

Task 8 =0

Task 9 =0

Task 10  =0

Task 11  =0

Task 12  =0

Task 13  =0

Task 14  =0

Task 15  =0

Quetion 2

Schedule variance (SV): The difference between the amounts budgeted for the work you actually did and for the work you planned to do. The SV shows whether and by how much your work is ahead of or behind your approved schedule.

Cost variance (CV): The difference between the amount budgeted and the amount actually spent for the work performed. The CV shows whether and by how much you’re under or over your approved budget.

SPI = Schedule performance index Earned value (EV) / Planned value (PV) (Shown in table )

CPI = EV/AC (Shown in table )

EAC = Estimate at completion

EAC = Approved budget for the entire task – Cost variance for the work done to date on the task

       = Budget at completion (BAC) + Actual cost (AC) – Earned value (EV)

= 142 + 68 - 59

= 151

ETC = Estimate to complete

ETC = Budget at completion (BAC) – Actual costs to date (AC)

= 142 - 68

= 74

VAC =Variance at Completion

=142 - 151

=-9

The Value of ETC is positive.

The value of EAC is positive.

The value of SPI/CPI is positive.

The Value of VAC is negative.

1 2 3 4 5 6 7
Activity Budget PV EV AC SV CV
4-3 4-5
Task 1 8 8 8 10 0 -2
Task 2 10 10 10 12 0 -2
Task 3 4 4 4 3 0 1
Task 4 12 12 12 12 0 0
Task 5 6 6 6 8 0 -2
Task 6 18 16 16 0 0 16
Task 7 6 6 3 6 -3 -3
Task 8 12 12 0 2 -12 -2
Task 9 10 10 0 0 -10 0
Task 10 6 6 0 3 -6 -3
Task 11 8 8 0 0 -8 0
Task 12 10 12 0 0 -12 0
Task 13 12 12 0 12 -12 -12
Task 14 12 14 0 0 -14 0
Task 15 8 8 0 0 -8 0
BAC 142 68
Question #2 Under \
Question #2 Under \
Question #2 Under \
Question #2 Under \
Question #2 Under \

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site