Use the following network with activities and times estimated in days to answer the questions below. If the diagram does not render open the attachment.
Activity
Optimistic
Most
Probable
Pessimistic
A
2
5
6
B
1
3
7
C
6
7
10
D
5
12
14
E
3
4
5
F
8
9
12
G
4
6
8
H
3
6
8
I
5
7
12
J
12
13
14
K
1
3
4
Be sure to show your diagram with ES, LS, EF, and LFs to receive full credit.
A. What are the critical path activities? (3pts)
B. What is the expected time to complete the project? (4pts)
C. What is the probability the project will take more than 28 days to complete? (3pts)
| Activity | Optimistic | Most Probable | Pessimistic |
| A | 2 | 5 | 6 |
| B | 1 | 3 | 7 |
| C | 6 | 7 | 10 |
| D | 5 | 12 | 14 |
| E | 3 | 4 | 5 |
| F | 8 | 9 | 12 |
| G | 4 | 6 | 8 |
| H | 3 | 6 | 8 |
| I | 5 | 7 | 12 |
| J | 12 | 13 | 14 |
| K | 1 | 3 | 4 |