Question 1 A project team member is performing some whatif a

Question 1

A project team member is performing some what-if analysis against the schedule before he submits it for approval. What general tool and technique is he performing?

Select one:

a. Schedule network analysis

b. Schedule compression

c. Schedule model data analysis

d. Resource analysis

Question 2

Negative float is associated with what?

Select one:

a. Resource intensity

b. Resource leveling

c. Schedule problem

d. Schedule leveling

Question 3

Inclement weather has consumed the slack in Shane\'s project, and a critical activity is now three days behind schedule. The customer must have delivery on the date originally promised, and the project\'s budgeted cost can\'t be changed. Which of the following actions are options for him to consider?

Select one:

a. Crash the schedule

b. Resource leveling

c. Perform Monte Carlo analysis

d. Fast-track activities

Question 4

Hachi has to make sure that an activity is completely done by a specific date before a dependent activity can begin. What constraint should she put on the first activity?

Select one:

a. SNLT

b. SNET

c. FNLT

d. FNET

Solution

Answer 1 c. Schedule model data analysis

Answer 2. c. Schedule problem

Answer 3. d. Fast-track activities

Answer 4. FNET

Question 1 A project team member is performing some what-if analysis against the schedule before he submits it for approval. What general tool and technique is
Question 1 A project team member is performing some what-if analysis against the schedule before he submits it for approval. What general tool and technique is