When discussing the BCP critical resources are usually divid

When discussing the BCP, critical resources are usually divided into five primary categories. The categories are which of the following groups?

A. Business, administrative, user, technical, and data

B. Administrative, policy, user, technical, and data

C. Business, facility and supply, user, technical, and nontechnical

D. Business, facility and supply, user, technical, and data

Solution

Answer :

Option D is correct

----------------------------------------------------------------------------------------------------------------

Explanation:

D. Business, facility and supply, user, technical, and data

When discussing the BCP, critical resources are usually divided into five primary categories. The categories are which of the following groups? A. Business, adm

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site