A production system has a burden rate of 280 per hour The se
A production system has a burden rate of $280 per hour. The setup time for a machined product is 30 minutes, and the system can produce a finished part every 10 minutes. For a lot size of 50 parts, determine the total cost per part? (Enter your answer without the dollar $ sign.)
Solution
setup time for a machined product is = 30 min
time for manufacturing for single product is = 10min
time for 50 product = 30+(50x10)
=530min
= 530/60
= 8.833hr
total cost = 280 x 8.83
=$2473.33