2 Using the primary DEP suppliers 60 percent o f business wh

2. Using the primary DEP suppliers (60 percent o f business), what is the minimum performance cycle for the supply chain diagrammed above? What is t he maximum?

Solution

2. Using the primary DEP suppliers (60 percent of business), what is the minimum performance cycle for the supply chain diagrammed above? What is the maximum?

Minimum Order Cycle time - 8 days (Calculate on time + time adjustment (min) (6+2)

Maximum Order Cycle time 25 days (6+6+5+4+4) Minimum on time cinsideration.

2. Using the primary DEP suppliers (60 percent o f business), what is the minimum performance cycle for the supply chain diagrammed above? What is t he maximum?

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site