2. Using the primary DEP suppliers (60 percent o f business), what is the minimum performance cycle for the supply chain diagrammed above? What is t he maximum?
Solution
2. Using the primary DEP suppliers (60 percent of business), what is the minimum performance cycle for the supply chain diagrammed above? What is the maximum?
Minimum Order Cycle time - 8 days (Calculate on time + time adjustment (min) (6+2)
Maximum Order Cycle time 25 days (6+6+5+4+4) Minimum on time cinsideration.