COURSE: CONSTRUCTION SCHEDULING/PLANNING

Which of the following factors should be used to determine the level of detail to include in a schedule during development?

Frequency of use

Products related to schedule (cost reports or progress payments).

Available time to produce schedule

Users

a.

Frequency of use

b.

Products related to schedule (cost reports or progress payments).

c.

Available time to produce schedule

d.

Users

Solution

Answer is option b.

Because based on the cost reports and the different progress stages, it is convenient to make a bill and contractor can claim it.

If the level of detail included in the scheduling is high, it makes easy to prepare bills which in turn depends on the availability of cost details of the individual tasks and payments to be paid to contractor at different stages of the project.

Therefore Products related to schedule(cost reports or progress payments) influences a lot to determine the level of detail to include in a schedule during development.