Course Construction ContractsSceduling Which of the followin

Course: Construction Contracts/Sceduling

Which of the following would be considered a major category of a WBS?

Erosion and sediment control

Sitework

Install carpet

Foundation formwork

a.

Erosion and sediment control

b.

Sitework

c.

Install carpet

d.

Foundation formwork

Solution

WBS : WORK BREAKDOWN STRUCTURE.

D. Foundation formwork is a major category of WBS