Hello could you please demontrate these questions I dont k
Hello , could you please demontrate these questions .
I dont know why dont we subtract 24,090,000 ( 16.5 Milion + 7.59 Milion ) from 18,000,000 ?
The following information relates to questions 104 and 105.
Cooper Construction Company had a contract starting April 2015, to construct a $18,000,000 building that is expected to be completed in September 2017, at an estimated cost of $16,500,000. At the end of 2015, the costs to date were $7,590,000 and the estimated total costs to complete had not changed. The progress billings during 2015 were $3,600,000 and the cash collected during 2015 was 2,400,000.
*104. For the year ended December 31, 2015, Cooper would recognize gross profit on the building of:
a. $632,500
b. $690,000
c. $810,000
d. $0
104. b ($18,000,000 – $16,500,000) ´ ($7,590,000 ÷ $16,500,000) = $690,000.
*105. At December 31, 2015 Cooper would report Construction in Process in the amount of:
a. $690,000
b. $7,590,000
c. $8,280,000
d. $7,080,000
*105. c $7,590,000 + $690,000 = $8,280,000.
Solution
Explanation:
Here Cooper Construction Company uses the percentage-of-completion method
104. b. 690000
(46% Complete; Gross profit of 1.5 m x 46% = 690,000)
105. C. 8280000
(Cost to date 7590000 + Gross Profit 690000)