It cost a contractor 12750 to manufacture their first unit T
| It cost a contractor $12,750 to manufacture their first unit. The company expects to experience a 92% unit learning curve. Estimate the cost of the 10th unit. (Round intermediate calculations to 4 decimal places) | 
| A) $15,661 | 
| B) $9,665 | 
| C) $10,380 | 
| D) $11,985 | 
| It cost a contractor $12,750 to manufacture their first unit. The company expects to experience a 92% unit learning curve. Estimate the cost of the 10th unit. (Round intermediate calculations to 4 decimal places) | 
| A) $15,661 | 
| B) $9,665 | 
| C) $10,380 | 
| D) $11,985 | 
Solution
B) $9,665