D Question 10 5 pts Anadarko Petroleum must choose between t
Solution
First we will calculate NPV for both projects at given WACC, at 12%.
NPV of Plan A= -12+14.4/1.12= $0.86
NPV of Plan B= -12+(2.10*((1-(1.12)^-20)/0.12)) = $3.69
The difference in NPV of the both project is $2.83
Crossover rate is the rate at which both Plans have equal NPV. This will be solved using hit and trail method as length of the plans are not equal.
at 15%.
NPV of Plan A= -12+14.4/1.15= $0.52
NPV of Plan B= -12+(2.10*((1-(1.15)^-20)/0.12)) = $1.14
The difference in NPV of the both project is $0.62
at 17%.
NPV of Plan A= -12+14.4/1.17= $0.31
NPV of Plan B= -12+(2.10*((1-(1.17)^-20)/0.12)) = $-0.18
The difference in NPV of the both project is -$0.49
Hence cross over rate is between 15 and 17%
at 16.07%.
NPV of Plan A= -12+14.4/1.1607= $0.41
NPV of Plan B= -12+(2.10*((1-(1.12)^-20)/0.12)) = $0.40
The difference in NPV of the both project is $0.01 whichis approx. equal to zero
Thus 16.07% is the answer
