Project S costs 11000 and its expected cash flows would be 6

Project S costs $11,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,500 and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend?

Select the correct answer.

a. Both Projects S and L, since both projects have IRR\'s > 0.
b. Both Projects S and L, since both projects have NPV\'s > 0.
c. Project S, since the NPVS > NPVL.
d. Project L, since the NPVL > NPVS.
e. Neither Project S nor L, since each project\'s NPV < 0.

Solution

NPV & IRR Project S Year Cash Flow DF for 16% Discounted Cash Flow FOR IRR 40% DF for 40% Discounted Cash Flow 0 -11000 1 $                    (11,000.00) 1 $                           (11,000.00) 1 6000 0.8621 $                         5,172.41 0.71429 $                               4,285.71 2 6000 0.7432 $                         4,458.98 0.51020 $                               3,061.22 3 6000 0.6407 $                         3,843.95 0.36443 $                               2,186.59 4 6000 0.5523 $                         3,313.75 0.26031 $                               1,561.85 5 6000 0.4761 $                         2,856.68 0.18593 $                               1,115.61 NPV $                         8,645.76 NPV $                               1,210.98 IRR =Ra + NPV @ Ra (Rb-Ra) Ra = Lower discount rate             NPV @ Ra - NPV @ Rb Rb = higher discount rate =0.16 + [ ((8645.76 X (.40 - .16)) / (8645.76 - 1210.98) =0.16 + (1.162881 X (.40 - .16)) 0.44 44% Project L Year Cash Flow DF for 16% Discounted Cash Flow FOR IRR 40% DF for 40% Discounted Cash Flow 0 -30500 1 $                    (30,500.00) 1 $                           (30,500.00) 1 14500 0.8621 $                       12,500.00 0.71429 $                             10,357.14 2 14500 0.7432 $                       10,775.86 0.51020 $                               7,397.96 3 14500 0.6407 $                         9,289.54 0.36443 $                               5,284.26 4 14500 0.5523 $                         8,008.22 0.26031 $                               3,774.47 5 14500 0.4761 $                         6,903.64 0.18593 $                               2,696.05 NPV $                       16,977.26 NPV $                                 (990.12) IRR =Ra + NPV @ Ra (Rb-Ra) Ra = Lower discount rate             NPV @ Ra - NPV @ Rb Rb = higher discount rate =0.16 + [ ((16977.26 X (.40 - .16)) / (16977.26 - (-990.123)) =0.16 + (0.944 X (.40 - .16)) 0.38 38% Based on NPV Project L is recommended Based on IRR Project S is recommended The Best way to select the project is NPV so project L is recommended
Project S costs $11,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,500 and its expected cash flows

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site