Question 3 Four hundred and eighty minutes of production tim
Question 3
Four hundred and eighty minutes of production time are available per day. Scheduled production is 120 units per day. What is the required cycle time?
4 minutes
5 minutes
6 minutes
7 minutes
4 points
Question 4
Suppose that the feasible region of a maximization LP problem has corners of (0,0), (10,0), (5,5), and (0,7). If profit is given to be $X + $2Y what is the maximum profit the company can earn?
0
10
15
24
| 4 minutes | ||
| 5 minutes | ||
| 6 minutes | ||
| 7 minutes |
Solution
Answer:- cycle time means how long you can complete a specific task from start to finish. this cylce time measure from stop watch.
480 minutes of production time available per day
schedule production is 120 units per day
cycle time = 480 minutes of production / 120 units
cycle time = 4 minutes
Answer:- Feasible region of a maximization of LP corners is (0,0), (10,0), (5,5) and (0,7)
when this corner points are shows, means 1st point is on X-axis and 2 point is on Y-axis, so lets put point in the profit equations.
The profit equation is $X + $2Y
corner (0,0) = $0 + $2(0) = 0
corner (10,0) = $10 + 2(0) = $10
corner (5,5) = $5 + $2(5) = $15
corner (0,7) = $0 + $2(7) = $14
so at the point (5,5), the maximum profit is on that.