Given is a Project with network diagram and activity times a
Given is a Project with network diagram and activity times as shown.
Activity
A
B
C
D
E
F
G
H
I
J
Time (wks)
2
8
5
8
5
14
6
4
7
8
 a) The Earliest Start (ES) time of Activity I =         weeks
 
 b) The Latest Start (LS) time of Activity B =          weeks
 
 c) The Slack time of Activity C =         weeks
 
 d) The Earliest Finish (EF) time of Activity H =             weeks
 
 e) The Latest Finish (LF) time of Activity B =        weeks
 
 f) The Project Completion time =        weeks
| Activity | A | B | C | D | E | F | G | H | I | J | 
| Time (wks) | 2 | 8 | 5 | 8 | 5 | 14 | 6 | 4 | 7 | 8 | 
Solution
A.The Earliest Start (ES) time of Activity I = 7 weeks
B.The Latest Start (LS) time of Activity B = 8 weeks
C. The Slack time of Activity C = 5 weeks
D.The Earliest Finish (EF) time of Activity H = 10 weeks
E.The Latest Finish (LF) time of Activity B = 1 weeks
F.The Project Completion time = 67 weeks