Shown below air the PERT schedule and the precedence relatio

Shown below air the PERT schedule and the precedence relationship among the activities required to complete a project. Setup the project activity network diagram for the following realationships in the table and determine the critical path. What is the probability id the company wants the project complete in more than 32 weeks?

Solution

 Shown below air the PERT schedule and the precedence relationship among the activities required to complete a project. Setup the project activity network diagr