ABCD company is an office equipment company that produces tw

ABCD company is an office equipment company that produces two types of desks: standard and deluxe. Deluxe desks have oak tops and more expensive hardware and require additional time for finishing and polishing. Standard desks require 80 square feet of pine and 10 hours of labor, while deluxe desks require 60 square feet of pine, 18 square feet of oak, and 16 hours of labor. For the next week, the company has 5,000 square feet of pine, 750 square feet of oak, and 400 hours of labor available. Standard desks net a profit of $150, while deluxe desks net a profit of $320. All desks can be sold to national chains Shops.

Required:

b. If the spreadsheet and Excel Solver results are given to you as follows (see Table 1 below), address the following questions:

What are your Binding Constraints?

What is your Optimum profit [hint: maximized profit]?

What are your slack values for Pine, Oak, & Labor?

Looking at the Shadow prices, how much would the objective profit increase by if you were to increase labor hours by 50?

If the optimum solution for Standard desk stays the same, but deluxe desk numbers increased. What would be your estimated deluxe desks in this case? Would you recommend this option? Why? Hints: Notice that by increasing labor hours by 50, the S stays as an original optimum solution given in the information of Solver, but D will increase. The question is asking you to find how much the objective profit would go up and what would be the estimated number for D [calculated from your constraints. Decimal number is accepted].

What would be the changes in objective profit $, if we increase the Pine by one unit and the Oak by one unit, i.e., Pine available=5001 & Oak available=751.

What % of available Oak can be reduced without it affecting the current given optimum solution?

What % of available Pine can be reduced without affecting the current (given) optimum solution?

How much should the standard desk unit profit of $150 be increased in order for Standard desks to be produced (i.e. become a positive number)?

Given results after developing the excel LP and Solver:

Excel program

Standard

Deluxe

Availability

Pine

80

60

5000

Oak

0

18

750

Labor

10

16

400

Profit/unit

$150

$320

Number produced

0

25.0

Total (per week)

Profit contribution

$0

$8,000

$8,000

Amount Used

Pine

1500

Oak

450

Labor

400

Solver Sensitivity Report:

Variable Cells

Final

Reduced

Objective

Allowable

Allowable

Cell

Name

Value

Cost

Coefficient

Increase

Decrease

$B$21

Number produced Standard

0

-50

150

50

1E+30

$C$21

Number produced Deluxe

25

0

320

1E+30

80

   Solver Constraints

Final

Shadow

Constraint

Allowable

Allowable

Cell

Name

Value

Price

R.H. Side

Increase

Decrease

$B$25

Pine Amount Used

1500

0

5000

1E+30

3500

$B$26

Oak Amount Used

450

0

750

1E+30

300

$B$27

Labor Amount Used

400

20

400

266.6666667

400

Standard

Deluxe

Availability

Pine

80

60

5000

Oak

0

18

750

Labor

10

16

400

Profit/unit

$150

$320

Solution

ABCD company is an office equipment company that produces two types of desks: standard and deluxe. Deluxe desks have oak tops and more expensive hardware and re
ABCD company is an office equipment company that produces two types of desks: standard and deluxe. Deluxe desks have oak tops and more expensive hardware and re
ABCD company is an office equipment company that produces two types of desks: standard and deluxe. Deluxe desks have oak tops and more expensive hardware and re
ABCD company is an office equipment company that produces two types of desks: standard and deluxe. Deluxe desks have oak tops and more expensive hardware and re