Given is a PERT project network diagram as shown below Activ
Solution
In the Pert alternate paths are given.
b) Earliest start time F =
This asks us to select starting F in the least time.
There are 3 roots for starting F, AF or BEF or CDEF
OF these we have to select one which has minimum time. As start time of F, we do not add time for F
AF = 10
BEF =11
CDEF = 29
Hence earliest activity for F = 10
------------------------------------------------------
c) For K
AFHK = 29
Obviously this will be minimum as AF is the earliest root
-----------------------------------------------------------
Latest start activity for E
CDE =22
BE =4
Hence latest is CDE =22
-------------------------------------------
e) The non critical activities mean where the roots are not more than 1
A, I, B, C, J, H, K,D
a) Project completion time is
AFHK = 44 or
BEFHK = 45 or
AGIK = 36 or
CDEGIK = 55
CJ = 33
Thus earliest is CJ
and longest is CDEGIK