A homeowner has had a bridge designed for a stream crossing

A homeowner has had a bridge designed for a stream crossing a privately owned road to their home. (They currently drive through the stream) The design is presented in the attached Sheets 1-5. You have just begun working as an assistant to the chief estimator for a construction firm that was asked to submit a proposal for the construction. The bridge to be built on a privately owned dead end road ¼ Mile in from a state road and within 10 miles of a city with adequate construction materials and equipment. All permits have been secured.
Owner will be away the months of May and June so there will be no traffic or temporary bridge requirements to deal with.

Based on the above information, what questions would you ask the engineer (RFI\'s)

Solution

SOLUTION:-

Based on the question information . the question would you ask the engineer(RFI\'s)

RFI\'s is Request for information that used in construction to clarify any uncertainess to fill any gap in infromation that may be found in any specfication constracts or other documents .

RFI\'s is needed when information from clinets designer or owener (stakeholder ) is insufficent bring up question or reqires clarification .

RFI is a integral part of the communication process No communication, whether it is written or verbal.

RFI set out :

After this set out and the given information in the question many question arising----

A homeowner has had a bridge designed for a stream crossing a privately owned road to their home. (They currently drive through the stream) The design is presen