Can you help me complete this network schedule I have alread
Can you help me complete this network schedule? I have already completed the drawing (diagram) of the activities.
| Activity | Predecessor | Duration | EarlyStart | EarlyFinish | LateStart | LateFinish | Slack |
| A | START | 3 | |||||
| B | START | 7 | |||||
| C | A | 4 | |||||
| D | B | 6 | |||||
| E | C, D | 5 | |||||
| F | E | 2 | |||||
| G | E | 8 |
Solution
Hence, the project completation in 17 days.