A tractormounted ripper will be used for excavating a limest
A tractor-mounted ripper will be used for excavating a limestone having a seismic velocity of 6000 ft/s. field tests indicate that the ripper can obtain satisfactory rock fracturing to a depth of 2 ft with one pass of a single ripper shank at 3 ft intervals. Average ripper speed for each 400 ft pass is 1.5 mph. Maneuver and turn time at the end of each pass average 3.0 min. Job efficiency is estimated at 0.70. Machine cost including the operator is $130/h. Estimate the hourly production and unit cost of excavation
Solution
(a) Hourly production:
It can be calculated by the formula: Production(BCY/n) = (2.22*D*W*L*E)/T
Here, D is average penetration depth=2 ft.
W is average with loosened = 3 ft.
L is length of pass = 400 ft.
E is job efficiency = 0.70
T is time for one ripper pass including turn = (400ft./1.5mph) + 3.0 min
convert mph to ft./min 1.5mph = 1.5*88 ft./min
T= 3.03 min + 3.0 min = 6.03 min
now put all values in main equation of production, we get
Prodduction = 2.22*2*3*400*0.70/6.03 BCY/h
= 618.50 BCY/h
(b) unit cost of excavation
total cost = $130/h
unit cost = ($130/h)/(618.50 BCY/h)
= $ 0.21/BCY