10.2 Examine the network schedule with its activities, their dura- tions, and initial cost plus extra cost for acceleration in the table. Draw its network diagram, determine the critical path, perform a time-cost trade-off analysis to minimize the total project duration and accelerated cost, and record your steps. AHS - 3 wk 3 wk 2 wk 2 wk 3 wk
Solution
Critical path means lonhest path of the activity.
Here the critical is...
A-B-C-G-H