For each of the four rows in Table 5101 organize and combine

For each of the four rows in Table 5.10-1, organize and combine the five columns of information together into one-to-two paragraphs that explain them in an easy-to-read format.

Table 5.10-1:

Risk Factor

(and Reason for

Significance)

Metrics

(and How Collected)

Risk Reduction/

Prevention Plan

Contingency

Plan

Entrance

Criteria

1. Requirements

stability.

(More people and

organizations (e.g.,

Navy, NATO) involved

means more time, more

requirements, and

requirements. instability

which leads to

cost/schedule slippage)

Track number of

requirements: original,

new, changed, deleted

(Count new, changed, and

deleted requirements every

month vs. previous month

by automated tool which

reads requirements

database)

Report requirements

stability with

written estimated

impact assessment

to all parties every

month and baseline

(freeze)

requirements at

planned time in

schedule

Reduce

functionality to

meet cost and

schedule or

increase funds and

schedule to

include

new/changed

requirements

If number of

changed req.

and number of

new

requirements

per month

exceeds 4

2: New Technology

(Learning curves for

OOD design techniques

and Ada language by the

development team will

take time; compiler

maturity for target

hardware (PCs) is low)

Count staff members

qualified in each discipline

(When staff member gets

minimum score on

OOD/Ada test or meets

other objective criteria)

1) Provide technical

training in OOD and

Ada;

2) Use and enforce

design and coding

standards

Employ OOD/Ada

expert

consultant(s) to

assist development

If the design or

coding

milestones fall

behind

schedule by

more than

15%

3: Reliability of

support organizations.

(Non-delivery of

required hardware and/or

materials will directly

impact on our ability to

deliver the complete system)

Production, installation,

and test milestones of each

required outside element

(Milestone progress

reports from all critical

suppliers and vendors)

Provide a bonus

structure to each

vendor and supplier

that is delivering a

required item for

delivering on time

Identify alternative

vendors and

suppliers and

purchase spares as

backup

Delta time

threshold over

2 weeks past

scheduled

delivery date

4: Overall system

testability.

(No test facility exists

that matches the real

system from beginning

to end as it exists in the

field.)

Percentage of Interfaces

tested and verified as

correct (Overall system

interface requirements

tracked through bi-weekly

status reports until

complete)

Develop a simulator

and test environment

that replicates as

nearly as possible

the whole system,

especially the

interfaces

Move testing to

field sites

If any required

interfaces

cannot be

tested in a

simulator

environment

by their

milestone due date

Risk Factor

(and Reason for

Significance)

Metrics

(and How Collected)

Risk Reduction/

Prevention Plan

Contingency

Plan

Entrance

Criteria

1. Requirements

stability.

(More people and

organizations (e.g.,

Navy, NATO) involved

means more time, more

requirements, and

requirements. instability

which leads to

cost/schedule slippage)

Track number of

requirements: original,

new, changed, deleted

(Count new, changed, and

deleted requirements every

month vs. previous month

by automated tool which

reads requirements

database)

Report requirements

stability with

written estimated

impact assessment

to all parties every

month and baseline

(freeze)

requirements at

planned time in

schedule

Reduce

functionality to

meet cost and

schedule or

increase funds and

schedule to

include

new/changed

requirements

If number of

changed req.

and number of

new

requirements

per month

exceeds 4

2: New Technology

(Learning curves for

OOD design techniques

and Ada language by the

development team will

take time; compiler

maturity for target

hardware (PCs) is low)

Count staff members

qualified in each discipline

(When staff member gets

minimum score on

OOD/Ada test or meets

other objective criteria)

1) Provide technical

training in OOD and

Ada;

2) Use and enforce

design and coding

standards

Employ OOD/Ada

expert

consultant(s) to

assist development

If the design or

coding

milestones fall

behind

schedule by

more than

15%

3: Reliability of

support organizations.

(Non-delivery of

required hardware and/or

materials will directly

impact on our ability to

deliver the complete system)

Production, installation,

and test milestones of each

required outside element

(Milestone progress

reports from all critical

suppliers and vendors)

Provide a bonus

structure to each

vendor and supplier

that is delivering a

required item for

delivering on time

Identify alternative

vendors and

suppliers and

purchase spares as

backup

Delta time

threshold over

2 weeks past

scheduled

delivery date

4: Overall system

testability.

(No test facility exists

that matches the real

system from beginning

to end as it exists in the

field.)

Percentage of Interfaces

tested and verified as

correct (Overall system

interface requirements

tracked through bi-weekly

status reports until

complete)

Develop a simulator

and test environment

that replicates as

nearly as possible

the whole system,

especially the

interfaces

Move testing to

field sites

If any required

interfaces

cannot be

tested in a

simulator

environment

by their

milestone due date

Solution

The answer is given in the paragraph form according to the information which is given in the table only.

1. Requirements stability.

The first risk factor is stability of requirements. In this more people and organizations like Navy, NATO etc. are involved which leads to increase the time factor. And because of this the number of requirements get increases. This will results into Instability which leads to slippage of cost/schedule. Now, this is collected by Tracking the number of requirements which can be original, new, changed or deleted and this can Count new, changed, and deleted requirements in every month vs. previous month by automated tool which reads requirements database.To reduce the risk factor, Report of requirements stability with written estimated impact assessment is prepared and send to all parties in every month and baseline or freeze requirements at planned time is scheduled. To plan the contingency functionality can be reduced to meet cost and schedule or increase in funds and schedule to include new/changed requirements can be done. For entrance criteria the number of changed requirements and number of new requirements per month should exceeds 4.

2: New Technology
The second risk factor is New Technology. This includes the learning of curves for OOD design techniques and Ada language by the development team. And this will take time which compiler maturity for target hardware (PCs) low. Now how it is collected? So, in this the staff members are counted who are qualified in each discipline on the basis of getting minimum score on OOD/Ada test or meets other objective criteria. The risk can be reduce by providing technical training in OOD and Ada and with the help of use and enforce design and coding standards.The contingency plan for this is to Employ OOD/Ada expert consultant(s) to assist the development. And the entrance criteria for this is, the design or coding milestones fall behind schedule by more than 15%.

3: Reliability of support organizations
   Now, the third reason for significance is reliability of support organizations which includes non-delivery of required hardware and/or materials which can give direct impact on our ability to deliver the complete system. And it is collected through the production, installation, and test milestones of each required outside element i.e. reports of milestone progress are collected from all critical suppliers and vendors.To prevent the risk, a bonus structure is provided to each vendor and supplier that is to deliver a required item for delivering it on time. The contingency plan for this is to Identify the alternative vendors and suppliers and purchase spares as a backup. And the entrance criteria for this is, the Delta time should threshold over 2 weeks past scheduled delivery date.

4: Overall system testability.
The fourth and the last risk factor is overall system testability. The reason behind the significance is there is no test facility exists that matches the real system from beginning to end as it exists in the field only. It is collected through the percentage of Interfaces tested and then verified as correct that means Overall system interface requirements are tracked through bi-weekly status reports until complete. This risk can be reduced by developing a simulator and test environment that replicates as nearly as possible the whole system, especially the interfaces.The contingency plan for this is to move the testing to the field sites. And the entrance criteria for this is any required interfaces cannot be tested in a simulator environment by their milestone due date.

For each of the four rows in Table 5.10-1, organize and combine the five columns of information together into one-to-two paragraphs that explain them in an easy
For each of the four rows in Table 5.10-1, organize and combine the five columns of information together into one-to-two paragraphs that explain them in an easy
For each of the four rows in Table 5.10-1, organize and combine the five columns of information together into one-to-two paragraphs that explain them in an easy
For each of the four rows in Table 5.10-1, organize and combine the five columns of information together into one-to-two paragraphs that explain them in an easy
For each of the four rows in Table 5.10-1, organize and combine the five columns of information together into one-to-two paragraphs that explain them in an easy
For each of the four rows in Table 5.10-1, organize and combine the five columns of information together into one-to-two paragraphs that explain them in an easy
For each of the four rows in Table 5.10-1, organize and combine the five columns of information together into one-to-two paragraphs that explain them in an easy

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site