Scenario You are slated to be the Resident Project Represent
Solution
The project has completed its conceptual design phase, that means the paper work has been done but the execution part is still incomplete, the project was scheduled for 24 months but it needs to be completed within 18 months as per the client demands, if the contractor is changed there would be some advantages and disadvantages as well
Advantages:
1. The project may be completed before time if the new contractor agrees as per the design
2. The cost of the project can be reduced by doing some adjustments in the design and planning
3. The owner is satisfied by the completion of work in time
Disadvantages:
1. As he is an A/E contractor, if the procedure starts again then there will be a lot of loss of time
2. Poor quality material may be used for completion of work in the time
3. Due to lack of time poor workmanship can affect the quality of material
4. If poor quality of material is delivered then it will not have any market value
So it is better to deliver good quality of material even if there is a delay of time, so it is better to not change the contractor.
The project can be completed in 18 months instead of 24 months by
1. Using huge number of man power
2. using large number of quality resources
3. ultimately increasing the manpower and resources leads to the increase in budget of the project
