Create a new base calendar named 7Day Calendar The Day Calen

Create a new base calendar named “7-Day Calendar.” The “-Day Calendar has working Saturdays and Sundays from 8 AM to 12 PM and 1 PM to 5 PM, 8 hours per day.

Change the project calendar to the 7-Day Calendar.

Answer the following questions.

What is the project completion date?

4 2H,2M 2H,2M 2H,2M 1M 2H,1M 1H,1M Activity Durationn LS EFI FF?TF LF 2H,3M 2H,2M

Solution

Solution

I)The network follow critical path A-D-E-F-H

So project complete in 16days

If consider the project satart date is=03/03/2018

Due to working days saturday and sunday

The project completion date is=22/04/2018

II) Project duration in working days is 8 hours per day

Create a new base calendar named “7-Day Calendar.” The “-Day Calendar has working Saturdays and Sundays from 8 AM to 12 PM and 1 PM to 5 PM, 8 hours per day. Ch