Create a new base calendar named “7-Day Calendar.” The “-Day Calendar has working Saturdays and Sundays from 8 AM to 12 PM and 1 PM to 5 PM, 8 hours per day.
Change the project calendar to the 7-Day Calendar.
Answer the following questions.
What is the project completion date?
4 2H,2M 2H,2M 2H,2M 1M 2H,1M 1H,1M Activity Durationn LS EFI FF?TF LF 2H,3M 2H,2MSolution
Solution
I)The network follow critical path A-D-E-F-H
So project complete in 16days
If consider the project satart date is=03/03/2018
Due to working days saturday and sunday
The project completion date is=22/04/2018
II) Project duration in working days is 8 hours per day