Project Management Answer the following questions A through

Project Management

Answer the following questions A through D. Use the Activity Predecessor Time below to create the path.

a. How many paths are there from the beginning of the network model to the end?

b. List the parts of each path

c. How long is each path?

d. Which is the critical path?

Activity Predecessor Time

A   - 10

B  - 7

C  A 8

D  - 10

E  B 10

F  E 9

G  C, D 10

Solution

(a) six

(b) A-START

B-B

C-C,A

D-D

E-EB

F-FE

G-G

(c)

(d) A<C<D<G

Project Management Answer the following questions A through D. Use the Activity Predecessor Time below to create the path. a. How many paths are there from the