Data The new pharmaceutical product that the company wishes

Data:

The new pharmaceutical product that the company wishes to introduce, Orchid Relief, uses two new ingredients. At this stage, Eli Orchid can procure limited amounts of each ingredient. The company has 4500 pounds of ingredient 1 and 3600 pounds of ingredient 2 available for this week.

Eli Orchid can manufacture the new product using any of its three existing processes that have different capabilities. The production with each of the processes is done in batches (a batch typically represents one full run of a machine from when it starts a task until it finishes it). Each batch of production by each of the processes uses different amounts of ingredients 1 and 2, and results in different number of units of Orchid Relief produced (note the difference between a batch and units of Orchid Relief produced). The table below outlines the cost per batch, amounts of the two ingredients required, and the number of units of Orchid Relief yielded per batch.

Process 1

Process 2

Process 3

Cost of production per batch

$14,000

$30,000

$11,000

Ingredient 1 required per batch (pounds)

180

120

540

Ingredient 2 required per batch (pounds)

60

420

120

Orchid Relief yielded per batch (units)

120

300

60

Eli Orchid needs to determine how many batches to produce with each process in the least costly way given the limited availability of the two ingredients. Also, the total production of Orchid Relief in units must be greater than or equal to the total forecasted demand (in units) for the following week.

The COO of the company asked the analyst[1]:

1. To use the new M3 model updated with week 9 data (d = 0.6568*Day -151.1703*Mon -136.2715*Tue -110.595*Wed -118.3629*Thu -74.7975*Fri + 1.7679*Sat + 434.5675) to predict the total demand (in units) for Week 10 (days 64-70).

M3

Mon.

Tue.

Wed.

Thu.

Fri.

Sat.

Sun.

TOTAL:

2. To state if this is a maximization or a minimization optimization problem?

3. To provide the mathematical formulation of the objective function assuming that X1, X2, and X3 are the decision variables representing the number of batches of each process to be used.

4. To provide the mathematical formulation of the model constraints.

Supply of ingr. 1

Supply of ingr. 2

Units produced

Non-negativity

X1, X2, X3 >= 0

Integer

X1, X2, X3 : Integer

5. To use the “Production” tab of the Excel file and complete the setup by:

entering the forecasted total demand in the pink cell

entering formulas in the five grey cells based on the mathematical formulation

Excel Formulas:

Cost of Production

Supply of Ingr. 1

Unit Cost

6. To set up Excel Solver (Assume Constraint Precision of 0.000001 and Integer Optimality (%) of 0) and provide the solution to the optimization problem.

Number of batches

Process 1

Process 2

Process 3

Cost of production (obj.)

Unit cost ($###.##)

7. To label each constraint in the solution as binding or not-binding.

Supply of ingr. 1

Supply of ingr. 2

Units produced

8. To consider a possible shortage of ingredients in the following week. What would the optimized production process look like if Eli Orchard could only procure 4320 pounds of Ingredient 1 and 1440 pounds of Ingredient 2?

Number of batches

Process 1

Process 2

Process 3

Cost of production (obj.)

Unit cost ($###.##)

9. To label each constraint in the new solution (for the shortage of ingredients) as binding or not-binding.

Supply of ingr. 1

Supply of ingr. 2

Units produced

10. To make recommendations about the production processes and pricing of Orchid Relief.

Note: this paragraph must fit on page 3. The entire project report (with the original description) must fit on 3 pages.

[write your paragraph here]

[1] Round numbers to four decimal points (e.g. 0.1234), unless explicitly requested otherwise.

Day Date Weekday Daily Demand Day Mon Tue Wed Thu Fri Sat
1 4/25/2016 Mon 297 1 1 0 0 0 0 0
2 4/26/2016 Tue 293 2 0 1 0 0 0 0
3 4/27/2016 Wed 327 3 0 0 1 0 0 0
4 4/28/2016 Thu 315 4 0 0 0 1 0 0
5 4/29/2016 Fri 348 5 0 0 0 0 1 0
6 4/30/2016 Sat 447 6 0 0 0 0 0 1
7 5/1/2016 Sun 431 7 0 0 0 0 0 0
8 5/2/2016 Mon 283 8 1 0 0 0 0 0
9 5/3/2016 Tue 326 9 0 1 0 0 0 0
10 5/4/2016 Wed 317 10 0 0 1 0 0 0
11 5/5/2016 Thu 345 11 0 0 0 1 0 0
12 5/6/2016 Fri 355 12 0 0 0 0 1 0
13 5/7/2016 Sat 428 13 0 0 0 0 0 1
14 5/8/2016 Sun 454 14 0 0 0 0 0 0
15 5/9/2016 Mon 305 15 1 0 0 0 0 0
16 5/10/2016 Tue 310 16 0 1 0 0 0 0
17 5/11/2016 Wed 350 17 0 0 1 0 0 0
18 5/12/2016 Thu 308 18 0 0 0 1 0 0
19 5/13/2016 Fri 366 19 0 0 0 0 1 0
20 5/14/2016 Sat 460 20 0 0 0 0 0 1
21 5/15/2016 Sun 427 21 0 0 0 0 0 0
22 5/16/2016 Mon 291 22 1 0 0 0 0 0
23 5/17/2016 Tue 325 23 0 1 0 0 0 0
24 5/18/2016 Wed 354 24 0 0 1 0 0 0
25 5/19/2016 Thu 322 25 0 0 0 1 0 0
26 5/20/2016 Fri 405 26 0 0 0 0 1 0
27 5/21/2016 Sat 442 27 0 0 0 0 0 1
28 5/22/2016 Sun 454 28 0 0 0 0 0 0
29 5/23/2016 Mon 318 29 1 0 0 0 0 0
30 5/24/2016 Tue 298 30 0 1 0 0 0 0
31 5/25/2016 Wed 355 31 0 0 1 0 0 0
32 5/26/2016 Thu 355 32 0 0 0 1 0 0
33 5/27/2016 Fri 374 33 0 0 0 0 1 0
34 5/28/2016 Sat 447 34 0 0 0 0 0 1
35 5/29/2016 Sun 463 35 0 0 0 0 0 0
36 5/30/2016 Mon 291 36 1 0 0 0 0 0
37 5/31/2016 Tue 319 37 0 1 0 0 0 0
38 6/1/2016 Wed 333 38 0 0 1 0 0 0
39 6/2/2016 Thu 339 39 0 0 0 1 0 0
40 6/3/2016 Fri 416 40 0 0 0 0 1 0
41 6/4/2016 Sat 475 41 0 0 0 0 0 1
42 6/5/2016 Sun 459 42 0 0 0 0 0 0
43 6/6/2016 Mon 319 43 1 0 0 0 0 0
44 6/7/2016 Tue 326 44 0 1 0 0 0 0
45 6/8/2016 Wed 356 45 0 0 1 0 0 0
46 6/9/2016 Thu 340 46 0 0 0 1 0 0
47 6/10/2016 Fri 395 47 0 0 0 0 1 0
48 6/11/2016 Sat 465 48 0 0 0 0 0 1
49 6/12/2016 Sun 453 49 0 0 0 0 0 0
50 6/13/2016 Mon 307 50 1 0 0 0 0 0
51 6/14/2016 Tue 324 51 0 1 0 0 0 0
52 6/15/2016 Wed 350 52 0 0 1 0 0 0
53 6/16/2016 Thu 348 53 0 0 0 1 0 0
54 6/17/2016 Fri 384 54 0 0 0 0 1 0
55 6/18/2016 Sat 474 55 0 0 0 0 0 1
56 6/19/2016 Sun 485 56 0 0 0 0 0 0
57 6/20/2016 Mon 311 57 1 0 0 0 0 0
58 6/21/2016 Tue 341 58 0 1 0 0 0 0
59 6/22/2016 Wed 357 59 0 0 1 0 0 0
60 6/23/2016 Thu 363 60 0 0 0 1 0 0
61 6/24/2016 Fri 390 61 0 0 0 0 1 0
62 6/25/2016 Sat 490 62 0 0 0 0 0 1
63 6/26/2016 Sun 492 63 0 0 0 0 0 0
64 6/27/2016 Mon 64 1 0 0 0 0 0
65 6/28/2016 Tue 65 0 1 0 0 0 0
66 6/29/2016 Wed 66 0 0 1 0 0 0
67 6/30/2016 Thu 67 0 0 0 1 0 0
68 7/1/2016 Fri 68 0 0 0 0 1 0
69 7/2/2016 Sat 69 0 0 0 0 0 1
70 7/3/2016 Sun 70 0 0 0 0 0 0

Solution

1) Using M3 model

        Mon : Variables Day = 64 , Mon = 1

                   Hence Demand of Monday = 64*0.6568 - 151.1703*1 + 434.5675 = 325.4324

       Tue : Demand of Tuesday = 65*0.6568 - 136.2715*1 + 434.5675 = 340.988

       Wed : Demand of Wednesday = 66*0.6568 - 110.595*1 + 434.5675 = 367.3215

      Thur : Demand of Thursday = 67*0.6568 - 118.3629*1 + 434.5675 = 360.2102

      Fri : Demand of Friday = 68*0.6568 - 74.7975*1 + 434.5675 = 404.4324

     Sat : Demand of saturday = 69*0.6568 + 1.7679*1 + 434.5675 = 481.6546

     Sun : Demand of sunday = 70*0.6568 + 434,5675 = 480.5085

    Total demand for the week = 2860.5476

2) It is a minimizing problem since we have to minimize the cost of production of Eli Orchid.

3) Objective function : Minimize (14000X1 + 30000X2 + 11000X3)

4) Model constraints: Supply of ingredient1 : 180X1 + 120X2 +540X3 <= 4500

                                    Supply of ingredient2 : 60X1 + 420X2 + 120X3 <= 3600

                                    Units produced : 120X1 + 300X2 + 60X3 >= 2861

                                    Non negativity : X1,X2,X3 >=0

                                   Integers : X1, X2, X3

Data: The new pharmaceutical product that the company wishes to introduce, Orchid Relief, uses two new ingredients. At this stage, Eli Orchid can procure limite
Data: The new pharmaceutical product that the company wishes to introduce, Orchid Relief, uses two new ingredients. At this stage, Eli Orchid can procure limite
Data: The new pharmaceutical product that the company wishes to introduce, Orchid Relief, uses two new ingredients. At this stage, Eli Orchid can procure limite
Data: The new pharmaceutical product that the company wishes to introduce, Orchid Relief, uses two new ingredients. At this stage, Eli Orchid can procure limite
Data: The new pharmaceutical product that the company wishes to introduce, Orchid Relief, uses two new ingredients. At this stage, Eli Orchid can procure limite

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site