Scrum makes heavy use of PERT/CPM networks to schedule s/w project efforts. a. true b. false
Solution
This is true. CPM or Critical Part method is used to find the minimum total project duration.
PERT or Program Evaluation and review technique is used to check the activity duration for each phases in the project. These two go hand in hand are used in scrum to effectively handle the project.