Immediate Predecessor Activity Time days 1 What is the lates
Immediate
Predecessor
Activity Time
(days
1. What is the latest time that activity E can be started without delaying the completion of the project?
A: 7 B: 3 C: 8 D:9
2. What is the latest finish time for activity F?
A: 7 B:16 C: 13 D: 9
3. What is the latest time that activity B can start without delaying the project?
A: 0 B: 8 C: 7 D: 4
4. What is the latest time that activity B can finish without delaying any other activities?
A: 0 B: 4 C: 8 D: 9
| Activity | Immediate Predecessor | Activity Time (days |
| A | - | 3 |
| B | - | 4 |
| C | A | 4 |
| D | A | 6 |
| E | B | 5 |
| F | C,D | 4 |
| G | E,F | 7 |
Solution
1. What is the latest time that activity E can be started without delaying the completion of the project?
D: 9
2. What is the latest finish time for activity F?
C: 13
3. What is the latest time that activity B can start without delaying the project?
A: 0
4. What is the latest time that activity B can finish without delaying any other activities?
B: 4