Immediate Predecessor Activity Time days 1 What is the lates

Immediate

Predecessor

Activity Time

(days

1. What is the latest time that activity E can be started without delaying the completion of the project?

A: 7    B: 3      C: 8     D:9

2. What is the latest finish time for activity F?

A: 7      B:16     C: 13     D: 9

3. What is the latest time that activity B can start without delaying the project?

A: 0      B: 8      C: 7      D: 4

4. What is the latest time that activity B can finish without delaying any other activities?

A: 0     B: 4      C: 8      D: 9

Activity

Immediate

Predecessor

Activity Time

(days

A - 3
B - 4
C A 4
D A 6
E B 5
F C,D 4
G E,F 7

Solution

1. What is the latest time that activity E can be started without delaying the completion of the project?

D: 9

2. What is the latest finish time for activity F?

C: 13   

3. What is the latest time that activity B can start without delaying the project?

A: 0   

4. What is the latest time that activity B can finish without delaying any other activities?

B: 4