Given the pay-off table below, determine the appropriate decision under uncertainty using:

Minimax Regret

States of Nature-Outcomes

Alternatives

Very Favorable

Average

Unfavorable

Build New Plant

$350,000

$240,000

-$300,000

Subcontract

$180,000

$90,000

-$20,000

Overtime

$110,000

$60,000

-$10,000

Do Nothing

$0

$0

$0

States of Nature-Outcomes

Alternatives

Very Favorable

Average

Unfavorable

Build New Plant

$350,000

$240,000

-$300,000

Subcontract

$180,000

$90,000

-$20,000

Overtime

$110,000

$60,000

-$10,000

Do Nothing

$0

$0

$0

Solution

Solution :

Applying the minimax regret criteria the minimum regret value happens to be $ 170,000 and it is associated with the decision alternative subcontract . The table is shown below : -

Alternatives Very Favorable Average Unfavorable
Build New Plant $0 $0 $290,000
Subcontract $170,000 $150,000 $10,000
Overtime $240,000 $180,000 $0
Do Nothing $350,000 $240,000 ($10,000)
Given the pay-off table below, determine the appropriate decision under uncertainty using: Minimax Regret States of Nature-Outcomes Alternatives Very Favorable
Given the pay-off table below, determine the appropriate decision under uncertainty using: Minimax Regret States of Nature-Outcomes Alternatives Very Favorable