dvantages to pursuing a fast track approach for the developm
Solution
Fast track project approach meant to be very fast to save client\'s money by reducing construction time.As construction time reduces the net labour cost reduces and also the client can move in or lease out that project immediately after the work completion, there by the client can earn profit earlier than they expected.
Advantages
* All the works related to project should be handled intelligently so efficient and skilled labour is needed for the entire project team
*We can save money and time
* In the compressed time schedule every one related to the project had knowledge related to each and every part of the project
* we can reduce unnecessary delay during a project
* good comunication is needed between the client , contractor and designer
*we can save money through advance purchase
following table shows the details of a traditional project schedule
The following table shows the updated fast track project schedule
From the above 2 tables we can found out that, for the traditional project schedule, the work can complete only by 8 days . But in the updated fast track project schedule the project can be complete with in 6 days. From that we can say that the work can be complete before the actual schedule. So that we can achieve the above mentioned advantages in that project.
| Day 1 | Activity 1 | Start |
| Day 2 | Activity 1 | Finish |
| Day 3 | Activity 2 | Start |
| Day 4 | Activity 2 | Finish |
| Day 5 | Activity 3 | Start |
| Day 6 | Activity 3 | Continue |
| Day 7 | Activity 3 | Continue |
| Day 8 | Activity 3 | Finish |