Problem 1:
length of pool = 50 meters
width of pool = 25 meters
depth of pool = 6 feet = 1.8288 meters
volume of water needed to fill pool = 50*25*1.8288=2286 m3
We know 1m3 = 264.172 gallons
Therefore, 2286 m3 = 603897.3 gallons
Ansswer is 603891.3 gallons
Problem 2:
volume of water required in gallons = 603891.3
volume of water required in liters = 2285977.243 liters
rate of filling of water = 8 liters/s
total time required to fill swimming pool = 2285977.243/8=285747.16 seconds = 3.31 days
Problem 3:
weight of truck = 2.27 tons = 22261.1 Newton
number of tyres = 4
weight on each tyre = 22261.1/4 = 5565.27 N
pressure =206.85 kPa=206.85*1000=206850 N/m2
contact area of each tyre= 5565.27/206850=0.027 m2 = 41.85 in2
Total contcat area including all four tyres = 4*41.85=167.4 in2
Problem 4:
Let us ddetermine the total area of wall required
Area of wall, without considering window, in each storey = 2*(100*12 + 50*12)=3600 ft2
Area of one window = 2*4=8 ft2
Number of windows in each storey = 35
Total area of window in each storey = 35*8=280 ft2
net area of wall in one floor = 3600-280=3320 ft2
Number of floors = 4
Total area of wall=4*3320=13280 ft2
Cost of material and installation per square ft = $10.51
Total cost = 13280*$10.51=$139572.8