Consider the following project baseline Numbers under each w
Consider the following project baseline
Numbers under each week show how much you plan to spend for the respective task in that week. For example, you plan to spend $16,000 for task B in week 3.
You are given the following status information at the end of week 5.
PLEASE slove in excel and send document to pdxsneakerhead@gmail.com
Question 1)Develop a status report and calculate Total PV, EV, PV, CV and SV for each task and the overall project.
Question 2) Calculate CI and SI for the overall project. Based on project SI and CI, what’s your assessment for the current status of the project?
Question 3) Calculate BAC, ETC and EAC for the overall project? How big is the project budget variance at completion (VAC)? Do you need extra money at completion?
Solution
1. Planned value= 50% of the value of the total work
PV= 50/100 * 16000
= 8000 USD
Earned value= 40% of value of the total work
= 40/100 *16000
= 6400 USD
Actual cost = 65 USD spent so far
CV = EV -AC
= 6400 - 65
= 6335
BAC = PV +AV +AC
= 8000 + 65 + 16000
= 24065 USD
CI = EV /AC = 6400/65 = 98.4
SI = EV / PV = 6400/8000 = 0.8
BAC = 16000 USD
ETC = estimate at completion - Actual cost
= 16000- 65
= 15935 USD
EAC = BAC / CPI
= 16000/98.4
= 162.6 USD