2 The time that takes to complete a certain type of construc
2. The time that takes to complete a certain type of construction projects has a mean of 35.5 months and a standard deviation of
1.5 months.
a. According to the Tchebysheff’s theorem, at least what percentage of these projects must have taken between 26.5 months
and 44.5 months to complete?
Work:
b. If in addition we are told that the relative frequency curve for the completion times is a bell-shaped curve, then
approximately what percentage of these projects would take more than 34 months to completed?
Work:
c. If the z-score for the completion time of a project is -2.6, find the completion time for that project.
Solution
a)
According to the theorem, at least 1 - 1/k^2 lie within k standard deviations from the mean.
Here,
k = (x - u) / s = (26.5 - 35.5)/1.5 = -6
Thus at least 1 - 1/k^2 = 1 - 1/6^2 = 0.972222222 = 97.22222% [ANSWER]
*********************
b)
We first get the z score for the critical value. As z = (x - u) sqrt(n) / s, then as
x = critical value = 34
u = mean = 35.5
s = standard deviation = 1.5
Thus,
z = (x - u) / s = -1
Thus, using a table/technology, the right tailed area of this is
P(z > -1 ) = 0.841344746 = 84.13% [answer]
***************************
c)
As
x = u + z*sigma,
x = 35.5 + (-2.6)*1.5
x = 31.6 [answer]
