With RUP Scrum and timeboxed scheduling the releases that ar

With RUP, Scrum, and time-boxed scheduling, the releases that are generated by each iteration: a. should be comprised of executable code b. need to go through rigorous customer acceptance testing c. should be traceable to elements of the WBS contained in the master plan d. can be documents and artifacts

Solution

Ans: C - should be traceable to elements of the WBS contained in the master plan

A work breakdown structure is a key project deliverable that organizes the team\'s work into manageable sections. The Project Management Body of Knowledge (PMBOK) defines the work breakdown structure as a \"deliverable oriented hierarchical decomposition of the work to be executed by the project team.\" The work breakdown structure visually defines the scope into manageable chunks that a project team can understand, as each level of the work breakdown structure provides further definition and detail.

With RUP, Scrum, and time-boxed scheduling, the releases that are generated by each iteration: a. should be comprised of executable code b. need to go through r

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site