The techniques and logic were created to plan for the mater

The ___ techniques and logic were created to plan for the material required to support the production of the master schedule. a. MTO b. MRP c. MPC d. MPS

Solution

The Answer is (b) - MRP

Explanation :- MRP is Material requirement planning, is a group of techniques that are useful to manage material requirement for large and short scale production, it also controls unnecessary inventory and avoids delay in production due to unavailability of materials. .

MRP system is effective tool for manufacturing/production planning and scheduling.

The ___ techniques and logic were created to plan for the material required to support the production of the master schedule. a. MTO b. MRP c. MPC d. MPSSolutio

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site