In an effort to meet its obligation under the Kyoto agreemen
Solution
Given that plant will be installed = 200 MW.
Cost of generation will be given by governement = 35 $/MWh
Electrical Energy output per year from the plant at given location Power output*Hours= 1700*200 + (0.75*200)*1200 + (0.5*200)*850 + (0.25*200)*400 + 0 = 625,000 MWh/year.
Installation cost of the plant = 850 $/kW.
Total cost of the whole plant of 200 MW = 850*200*1000 = 170,000,000 $ .
Life time of Plant is 30 Years.
Energy generated in 30 Years = 625,000*30 = 18,750,000 MWh.
Total amount paid in one year by governement = 35 * 625,000 = 21,875,000 $.
Percentage of return per year = (Total Amount paid by government per year / Total Installed Cost)*100
= (21,875,000 / 170,000,000) * 100 = 12.867647 % .
This percentage of return is more than company minimum acceptable percentage of return = 12%.
Hence the company will take government offer to setup power plant.