Given the following information what is the cost of unused c



Given the following information, what is the cost of unused capacity? Cost of material supplied is $8,600; Cost of material used is e, s600 $8,000; Cost of material used per shelf is $8 Cost of material supplied per shelf is $8.60 $1,000. e $0.60. $6,000. There is no unused capacity

Solution

Cost of unused capacity = materials supplied - materials used

   = 8,600 - 8,000

   = $600 answer

Cost of unused capacity = materials supplied - materials used

   = 8,600 - 8,000

   = $600 answer