A project which costs S42000 pron Points 5 es S 15000 in the
     A project which costs S42,000 pron (Points: 5) es S 15,000 in the first period, $5000 Ln he third period, s 16,000 in the fourth period and $14,000 in the fifth period IfWACC is 55% what is the NPV of this project? O 103.43 O 98.03 O negative 10,774.54 O negative 11,367.14 O negative 103.43     

 
  
  Solution
Correct option is > 103.43
Working:
Year
Cash flows = CF
Df = 1/(1+5.5%)^Year
Present Value = CF x Df
0
-42,000.00
1.000000
-42,000.00
1
15,000.00
0.947867
14,218.01
2
0.00
0.898452
0.00
3
5,000.00
0.851614
4,258.07
4
16,000.00
0.807217
12,915.47
5
14,000.00
0.765134
10,711.88
Total PV = NPV =
103.43
NPV is sum of Present value of all cash flows as worked above.
| Year | Cash flows = CF | Df = 1/(1+5.5%)^Year | Present Value = CF x Df | 
| 0 | -42,000.00 | 1.000000 | -42,000.00 | 
| 1 | 15,000.00 | 0.947867 | 14,218.01 | 
| 2 | 0.00 | 0.898452 | 0.00 | 
| 3 | 5,000.00 | 0.851614 | 4,258.07 | 
| 4 | 16,000.00 | 0.807217 | 12,915.47 | 
| 5 | 14,000.00 | 0.765134 | 10,711.88 | 
| Total PV = NPV = | 103.43 | 