Exercise 149 An incomplete cost of goods manufactured schedu
     Exercise 14-9 An incomplete cost of goods manufactured schedule is presented below Complete the cost of goods manufactured schedule for Hobbit Company. HOBBIT COMPANY Cost of Goods Work in process (1/1) Direct materials $215,370 Raw materials inventory (1/1) Add: Raw materials purchases Total raw materials available for use Less: Raw materials inventory (12/31) 164,870 27,100 $183,400 Direct materials used Direct labor Manufacturing overhead Indirect labor Factory depreciation Factory utilities Total overhead 21,960 36,430 71,750 130,140 Total manufacturing costs Total cost of work in process Less: Work in process (12/31) Cost of goods manufactured Click if you would like to Show Work for this question 88,810 $545,650 Question Attempts: 0 of 15 usedSAVE FOR LATER SUBMIT ANSWER     
 
  
  Solution
Cost of goods manufactured schedule :
| Work in process (1/1) | 215370 | ||
| Direct material | |||
| Raw material inventory (1/1) | 45630 | ||
| Add: Raw material purchases | 164870 | ||
| Total raw material available for use | 210500 | ||
| Less: Raw material inventory (12/31) | 27100 | ||
| Direct material used | 183400 | ||
| Direct labour | 105550 | ||
| Manufacturing overhead | |||
| Indirect labour | 21960 | ||
| Factory depreciation | 36430 | ||
| Factory utilities | 71750 | ||
| Total overhead | 130140 | ||
| Total manufacturing costs | 419090 | ||
| Total cost of work inn process | 634460 | ||
| Less: Work in process (12/31) | 88810 | ||
| Cost of goods manufactured | 545650 | ||